Sherwood Co-op Parliament Avenue Gas Bar and Carwash
Carwash (4,160 sq.ft):
Complete Drawing Package
Building excavation and pile installation
Grade beam, interceptor pit
Heated main building slab and apron slab
Prefinished Concrete filled wall panel
Hollow core roof floor
SBS roof system
100ft carwash conveyor pit
Monument and Pylon signs
Metal cladding, EIFS stucco and stacked stone
Window and door supply and installation
Mechanical and controls
Electrical systems
Site works (landscaping, asphalt)
C-Store (2,777 sq.ft):
Complete Drawing Package
Building excavation and pile installation
Grade beam and slab concrete work
Wood Framing, trusses, LVL
EPDM roof system
Metal cladding, EIFS stucco and siding
Window and door supply and installation
Drywall, suspended ceiling, and painting
Flooring, base and wall protection
FRP Panels
Millwork, office and shop furnishings
Washroom accessories and partitions
Mechanical and controls
Electrical systems
Site works (landscaping, asphalt, sidewalks)
Monument and Pylon signs
Gas Bar (3,490 sq.ft):
Complete Drawing Package
Canopy footprint excavation and pile installation
Concrete island slab
Structural steel columns
Petroleum and Petroleum tank nest
SBS Roofing
ACM cladding
Window and door supply and installation
Drywall, suspended ceiling, and painting
Flooring, base, and signage
FRP Panels
Millwork, office and shop furnishings
Washroom accessories and partitions
Mechanical and controls
Electrical systems
Site works (landscaping, asphalt, sidewalks)
Monument and Pylon signs
Location: Regina, SK
Building Area (sq.ft.): Car Wash: 4,160 Sq. Ft. - C-Store: 2,777 Sq. Ft. - Gas Bar: 3,490 Sq. Ft.
Date Completed: In Progress